Part I The decision: does it make sense?
Chapter 5: Will it pay off? The business case
On average, large IT projects deliver 56% less value than they promised McKinsey and Oxford, 2012. Moreover, the actual benefit is often not measured, because the goals were only phrased as “improving conditions.” A good business case compares the project with the “do nothing” option, quantifies the benefits in money, and sets 3–5 metrics with a baseline. And it has a single owner who is responsible for the benefits, also after launch.
Benefits are overestimated more than costs
The costs of large IT projects overrun the plan by 45% on average, while benefits fall short by 56% McKinsey and Oxford, 2012. The weakest part of a business case can therefore be the very benefits meant to justify the investment. For each benefit, write down who will measure it, how, and when. The calculation should use the total costs over 5 years from chapter 4, not the contract price. Otherwise, your payback period will come out years shorter than it really is.
A goal you cannot measure is not a goal
“Modernize and streamline our processes” sounds good, but you will never find out whether it worked. “Cut application processing time from 12 to 5 days by the end of 2027” is something you can measure. Set 3–5 metrics, and for each one state:
- the baseline value today (measure it before development starts),
- the target value and date,
- who measures it and where the data comes from.
Judge success by the metric values after 6 and 12 months of operation, not just by whether you launched the system on time.
Digitalization of the state without measurable goals (NKÚ 2026)
In 2020–2024, the state spent over CZK 50 billion on digitalization, yet only 18% of services are fully online (1,621 of 8,916). The Supreme Audit Office (NKÚ) assigned 87 audit findings to the “unmet objectives” barrier. Goals were often phrased as “creating conditions” without measurable indicators, so the benefit could not be verified. For eJustice, the Ministry of Justice met 2 of 20 goals NKÚ, 2026. The lesson: the money gets spent, but without metrics nobody can say what it produced.
Five types of benefits and how to calculate them
- Time saved: number of people × hours saved per week × number of working weeks × hourly cost. Count only part of the result as a benefit. Not every hour saved turns into other useful work.
- Fewer errors: number of errors per year × cost of one error (correction, complaint, fine) × expected reduction.
- Higher revenue: additional sales × margin, not total sales.
- Lower risk: probability of an event × its impact × how much the system reduces it.
- Legislation: the cost of the cheapest alternative way to meet the obligation. Not the amount of the fine.
Example: 20 people each save 2 hours a week. With a gross salary of CZK 80,000, an hour of work costs the employer about CZK 670 (salary × 1.338 for contributions, divided by 160 hours). Over 46 working weeks, that comes to CZK 1.23 million, and if only half of the time saved can be put to use, roughly CZK 615,000 a year. That is a number you can take to the finance director.
Add the savings from the old solution: licenses, support, and operations that will really go away. Then ask the key question: does the project pay off even if the benefits are halved and the costs are a quarter higher? If so, you have a strong business case.
Always compare with the “do nothing” option
Keeping the current state also costs money. The old system ages, its support gets more expensive, and outages loom. At the Ministry of Foreign Affairs (MZV), for example, the cost of supporting the old system rose from CZK 1.2 million to CZK 15.3 million a year NKÚ, audit conclusion KZ 24/26 (chapter 4). Without putting a number on the do-nothing option, you cannot judge whether the change pays off. So compare three options: keep the current state, buy or customize an off-the-shelf solution, and develop custom software (chapter 2).
A business case is not a one-off document. After discovery and after the first stage, you will know more. Recalculate it at both points. Submit every reduction in scope for approval again, together with its impact on the benefits. Otherwise the project may stay within budget but fail to serve its purpose.
Who is responsible for the benefits
A single sponsor from the business should be responsible for the benefits, also after launch. Do not shift this responsibility to the head of IT or to the vendor. The benefits are estimated and signed off by the process owner on your side.
The decision to continue should not rest only with the person who pushed the project through. A classic experiment showed that the most money is added to a failing choice by people who are personally responsible for the original decision Staw, 1976. So separate the person who runs the project from the person who assesses its status, and agree on stop criteria in advance.
Escalation of commitment: the more money and reputation have already gone into a project, the harder it is to stop. Decide based on criteria written down in advance, not on how much the project has already cost.
| How it goes wrong | How to do it right |
|---|---|
| How it goes wrongGoal: “modernize and streamline our processes.” | How to do it rightGoal: “cut application processing time from 12 to 5 days by the end of 2027.” |
| How it goes wrongThe vendor estimates the benefits in its proposal. | How to do it rightThe process owner on your side estimates and signs off the benefits. |
| How it goes wrongOnly “new system or nothing” is compared, without the cost of doing nothing. | How to do it rightThree options, including the cost of keeping the current state. |
| How it goes wrongCosts = contract price. | How to do it rightCosts over 5 years, including operations, further development, and internal time. |
| How it goes wrongScope gets cut, but the benefits in the presentation stay the same. | How to do it rightAfter every cut, the benefits are recalculated and approved again. |
| How it goes wrongThe project is assessed by the person running it. | How to do it rightStatus is assessed by someone independent; stop criteria are agreed in advance. |
- Until December 31, 2026, the obligation to demonstrate effectiveness, economy, and efficiency (3E) is set by Act No. 320/2001 Coll., on Financial Control.
- From January 1, 2027, it is replaced by Act No. 231/2025 Coll., on Management and Control of Public Finances. Its principle of sound financial management (Section 3) contains the same 3E: public funds must be handled effectively, economically, and efficiently Act No. 231/2025 Coll.. A business case built according to this chapter holds up under both acts.
- Ministry of Finance methodological guideline CHJ No. 3 (version 3.0 of September 1, 2026) is already based on the new act and assesses economy over the whole lifecycle MF, guideline CHJ No. 3, 2026.
- Effectiveness metrics and a cost-benefit analysis (CBA) serve as a basis for audits, including audits by NKÚ. For goals without indicators, NKÚ states that the benefit cannot be verified.
- For projects financed from EU funds, failing to meet goals risks a reduction of the grant. For eISIR, the managing authority of the Integrated Regional Operational Programme (IROP) withdrew almost half of the allocation NKÚ, 2026.