    Part II Preparation and vendor selection

    Chapter 10: Fixed price, T&M, or something in between?

    ~10 min readUpdated Lukáš Mikula (opens in a new window)

    A fixed price without a finished specification is an illusion: someone always pays for the risk of uncertainty, either as a premium in the proposal or through amendments. A fixed price suits small, well-described engagements. For a new system, a budget cap and a split into stages work well. Within each stage, you then pay for the time worked or per accepted increment.

    The risk of uncertainty does not disappear; it only moves

    In the idea phase, an estimate can be 0.25× to 4× the actual figure; you only get to about ±10% after a detailed design McConnell, 2006 and 2010 (chapter 1).

    If you want a fixed price for a whole system based on a two-page brief, you will get one of two kinds of proposal. Either it will contain a high risk premium, or it will be underestimated and the vendor will make up the difference later with additional work. Neither is a good deal.

    Each model just distributes the risk differently. With a fixed price, the vendor formally carries it, but in reality you pay for it in the premium. With time and materials (T&M), you carry it, but you only pay for work actually done. Combined models share the risk: the vendor is responsible for a stage, and you decide what comes next.

    Time works against you: each additional year of duration increases cost overruns by 15% McKinsey and Oxford, 2012. So split the project into smaller stages, roughly up to 3 months each. After each one, decide whether to continue.

    Pricing models for software development
    ModelWhen to useWho carries the riskTrap
    Fixed price and scopesmall, short, fully described engagements; migrations, implementation of an off-the-shelf productformally the vendor, in reality it comes back in the premiumunderpriced proposal, disputes over what is “in scope”
    Time and materials with a capa new service, unclear processes, a need for fast feedbackmainly the customerwithout a product owner, “burning hours”
    Fixed price in stagesmost new systems; the first stage fixed, further ones as optionssharedfor a public authority, only options reserved in the tender documentation
    Fixed budget and time, variable scopeagile development with a fixed budgetshared; the customer carries what does not fitwithout priorities, the scope gets out of control
    Payment per accepted incrementsprints with a clear Definition of Donethe vendor for what is not delivered, the customer for timely acceptanceslow acceptance blocks payments
    Fixed monthly feelong-term further development and operationsthe customer (capacity utilization)unused PD expire
    Framework agreementlarge modular systems, recurring needsshared; competition keeps the price downthe rules cannot be changed later

    Hybrid: a fixed frame, flexible content

    For most companies and public authorities, a combined model makes sense: a fixed budget cap, stages that end with a decision on the next steps, and agile development with a backlog within them. Priorities (MoSCoW, chapter 6) decide the content of a stage, and the price stays under control. The Czech adaptation of the 18F handbook recommends “continuous payments for time and costs (with a cap on total spending)” Česko.Digital, 2022.

    It works like renovating an apartment with a fixed budget: you know how much you can spend, and after each room you decide whether to continue the same way or differently.

    But time and materials without rules is an open budget. Watch four things:

    • a cap that the vendor will not exceed without your consent,
    • a monthly overview of budget spend in relation to what has been delivered and accepted,
    • the right to stop ordering at any time,
    • a product owner who has time to decide on priorities.

    Where you have a clear Definition of Done, you can pay per accepted increment: the vendor invoices only the parts you have tested and accepted. This works only if acceptance on your side does not stall. Otherwise, you delay payments and damage the collaboration.

    Decision tree

    Which pricing model?

    Four questions lead you to the model that matches how well you know your requirements.

    Are you looking for a vendor for a system that is already running (for its further development or operations)?

    That is, a long-term collaboration with no clear end, not a new project.

    Are you looking for a vendor for a system that is already running (for its further development or operations)?

    That is, a long-term collaboration with no clear end, not a new project.

    • Yes

      Fixed monthly fee or framework agreement

      A fixed monthly team capacity, or a framework with rates and orders as needed. Check exactly what you get for the fixed monthly fee and what happens to unused person-days. Chapter 22: Maintenance and further development →

    • No

      Are the requirements fully described and validated by a prototype or discovery?

      A vendor could calculate the effort from them without major assumptions.

      • Yes

        Fixed price and scope

        For a small, short, and well-described engagement, a fixed price makes sense. Ask for a list of assumptions and out-of-scope items with it, so it is clear what the price includes.

      • No

        Do you have a product owner who has time for the project and is allowed to make decisions?

        • Yes

          Do you need a fixed amount in advance (an approved budget, a public contract)?

          • Yes

            Fixed budget in stages

            A fixed cap and deadline, with a variable scope driven by priorities. Or a fixed price for the first stage and further stages as options. After each stage, you decide whether to continue.

          • No

            Time and materials with a cap

            You pay for person-days worked up to an agreed cap. The condition is a monthly overview comparing budget spend with delivered results, and the right to stop ordering at any time.

        • No

          Paid discovery first

          Without requirements and without a person who makes decisions, no model works. Order discovery for a fixed price, appoint a product owner, and then come back to these questions. Chapter 8: paid discovery →

    What a person-day and a whole team cost

    In the first half of 2026, the median rate per person-day in government contracts ranged from CZK 9,220 for a tester to CZK 13,600 for an architect, excluding VAT MV, overview of ICT rates, July 2026. You will find the table by role in chapter 4. Work with quartiles, not the average, and check whether you are comparing prices including or excluding VAT.

    According to Česko.Digital, a team of 5–9 people costs roughly CZK 12–20 million a year, and a single contract should not exceed CZK 40 million a year and 3 years Česko.Digital, 2022. An indicative check: 5 people × 20 PD × CZK 10,500 × 12 months = CZK 12.6 million a year.

    Pay only for accepted work

    Acceptance is the last moment when you have leverage. So agree on payments only after a stage has been accepted, and retention (retainage) until the end of the warranty, roughly 5–10% of the price. Contractual penalties for missed milestones are typically around 0.05–0.2% of the stage price per day, always with a cap (rule of thumb). Chapter 20 describes how to carry out acceptance. Chapter 18 covers changes during a stage.

    Red flags in a price proposal

    • A fixed price for the whole system without a list of assumptions.
    • A price or rate well below the others, with no explanation.
    • One average rate without a breakdown by role.
    • T&M without a cap and without a spend report.
    • An “agile” project in which every change is handled through an additional order.
    • After 2–3 sprints, there is nothing to see.
    How it goes wrongHow to do it right
    How it goes wrongA fixed price for the whole system based on a two-page brief.How to do it rightA fixed price for discovery and the first stage, further stages as options.
    How it goes wrongT&M without a cap, invoiced “for hours worked.”How to do it rightT&M with a cap and a monthly spend report against the accepted scope.
    How it goes wrongYou compare rates: CZK 8,000 vs. CZK 11,000.How to do it rightYou compare the total price of the delivery and the seniority. A cheap rate × more PD = a more expensive project.
    How it goes wrongA budget without contingency; every change is a crisis.How to do it rightContingency in the budget and change control with a management decision.
    How it goes wrongOne contract for 4 years.How to do it rightStages with a decision gate, a contract for at most 3 years (18F rule of thumb).
    How it goes wrongThe full price paid at handover.How to do it rightPayment after acceptance of stages, retention until the end of the warranty.

    Questions

    Questions for the vendor

    1. What assumptions apply to your price, and what happens if they do not hold?
    2. How do you price change requests?
    3. What experience do the people whose work you offer at this rate have?
    4. How many person-days go to management and testing?
    5. How will you compare budget spend with delivered results?
    6. What exactly will you show at the end of each sprint or stage?
    7. Can we stop after any stage, and what do we get at that point?